Attached is the 30 May 08
Mall Update:
-
400 BLOCK
o
Sidewalks against
buildings complete.
-
500 BLOCK
o
Pavers middle & west end.
o
Sprinkler lines
& finish grade.
o
Set drinking
fountain.
o
Grate drains.
o
Rework column
drains.
o
Column fixtures.
o
Landscape lights.
-
600 BLOCK
o
Sidewalks.
o
Drinking
fountain.
o
Grate drains.
o
Seat walls.
o
Sprinkler lines
& finish grade.
o
Pavers.
o
Column fixtures.
-
7TH
ST INTERSECTION
o
Curbs.
o
Sidewalks.
Mall update 20 May 08:
-
400 BLOCK
o
Sidewalks against
buildings.
-
500 BLOCK
o
Pavers middle & west end.
o
Seat walls.
o
Sprinkler Lines
& finish work.
o
Set drinking
fountain.
o
Grate drains.
o
Column fixtures.
-
600 BLOCK
o
Asphalt on 6th.
o
T-lock on 6th.
o
Sidewalks.
o
Seat wall
footings.
o
Drinking
fountain.
o
2 Grate drains.
o
Seat walls.
NOTE: At the 7th Street intersection
gravel has been put done so people can move east and west. At the 6th
Street intersection the walk ways have been opened both east and west.
Below is the 13 May 08 Mall
Update:
-
400 BLOCK
o
Sidewalks against
building.
o
Light pole bases.
o
Underground for
light poles.
-
500 BLOCK
o
Paver base east
side of 6th.
o
Sidewalk
northeast corner of 6th.
o
Bench & trash
can pads.
o
Pavers middle & west end.
o
Seat walls.
o
Sprinkler lines
& finish grade.
-
600 BLOCK
o
Base in 6th.
o
Asphalt in 6th.
o
Sidewalks.
NOTE: Most deficiencies noted last week, are in the
process of being corrected.
The following is 6 May 08
Mall update:
-
400
BLOCK
o
Sidewalk against
building.
o
Light pole bases
north side.
o
Underground for
light pole.
o
Build southeast
seat wall.
-
500 BLOCK
o
Paver base
against 6th St.
o
Bench & trash
can pads.
o
Landscape lights.
o
Sprinkler lines.
o
Finish grade.
-
600 BLOCK
o
Line H.
o
Column drains.
o
Drinking fountain
& quick coupler.
o
Grate drains.
o
Curbs on 7th
St.
o
Finish base.
Below is 2 May 08 Mall
Project update:
-
400 BLOCK
o
Control pit.
o
Underground for
fountain and tank.
-
500 BLOCK
o
Paver base.
o
Pavers.
-
600 BLOCK
o
Service lines.
o
Storm lines.
o
6th
St. base.
NOTE:
There has
been some corrections being done to the seat walls and 6th St.
intersection and adjourning sidewalks. Although this will take a little
time to correct, we are still planning on completion as scheduled.
Below is the Mall Project
update for 24 April, 2008:
-
400 BLOCK
o
Footings for seat
wall.
o
Seat wall west
end.
o
Sidewalk.
o
Grade for
fountain pad.
o
Underground
plumbing & electrical to pit.
-
500 BLOCK
o
Sidewalk.
o
Paver base.
o
Pavers east side.
o
Seat wall.
o
Sprinkler lines.
-
600 BLOCK
o
Finish
& hydro test main.
o
6th
St. curb.
o
Base.
o
Service lines
& storm lines.
o
Sidewalk.